Location |
|
|
|
MARCH AND APRIL 2010 |
|
|
 |
Installation of new reinforcing members in sector B2 above St-Laurence River. |
|
|
|
 |
New post tension steel bars are added under the Ramp 3, direction Chateauguay. |
|
|
|
 |
Those bars are tensioned with powerful hydraulic jacks. |
|
|
|
 |
The bars are anchored to the structure so that it can take the load of the new deck. |
|
|
|
 |
Platforms are installed under sector B2 in spans 3 and 4, near Montreal side. |
|
|
|
DECEMBER 2009 - FEBRUARY 2010 |
|
|
 |
In B2 sector, above St-Laurent’s river direction south shore, new members are installed to accommodate the loads of the new decks. |
|
|
|
 |
Steel plates are also required on diagonals, this photo show the amount of work to bolt those plates to the actual structure. |
|
|
|
 |
Steps to install those plates are: cleaning of existing steel, adjusting the plates, drilling holes in the existing steel structure and bolting.
|
|
|
|
 |
In Ramp 3, from Montreal to Chateauguay, steel structure is enlarged to accommodate the new bike path. |
|
|
|
 |
Detail of the floorbeam extensions.
We can also see that the installation of the bearing pedestals for the new decks is in progress.
|
|
|
|
NOVEMBER 2009 |
|
|
 |
Installation of the bridge deck waterproofing membrane. |
|
|
|
 |
Asphalt paving of Ramp 4. |
|
|
|
 |
Traffic marking. |
|
|
|
 |
Installation of electrical utilities. |
|
|
|
 |
November 30, 2009 : Opening ceremony. |
|
|
|
OCTOBER 2009 |
|
|
 |
On October 8th, 2009 the last panel in Ramp 4 is installed. |
|
|
|
 |
The connection between structure and panels has been concreted. |
|
|
|
 |
Concreting of the expansion joints. |
|
|
|
 |
The next step will be the concreting of the expansion joint’s barriers. |
|
|
|
 |
Situation of works on October 31st 2009. |
|
|
|
SEPTEMBER 2009 |
|
|
 |
After the installation of all the new deck panels in a span, it is time to concrete the constructions joints. |
|
|
|
 |
There are about 5 to 7 construction joints per span. |
|
|
|
 |
The next step is the post-tensioning of cables in the new deck. |
|
|
|
 |
Then the expansion joint is installed, waiting to be adjusted and concreted.
|
|
|
|
 |
Situation of works on September 30th 2009. |
|
|
|
|
|
AUGUST 2009 |
|
|
|
Reinforcing works at the steel substructure for the ramp that carry traffic from Chateauguay (ramps 4) have been completed. Steel works are going on at the steel substructure for the ramp that carries traffic to Chateauguay (Ramp 3). |
|
|
 |
Directly after the deck removal, bearing pads for the new deck are installed. |
|
|
|
 |
The first four spans, Montreal side, have been installed. |
|
|
|
 |
A second crane has been installed to accelerate the work. |
|
|
|
 |
Situation of works on August 31st 2009. |
|
|
|
JULY 2009 |
|
|
Steel works are in progress at the steel substructure for the two ramps that carry traffic to and from Chateauguay (ramps 4 and 3).
Deck replacement work started on July 22nd on the Montreal bound ramp from Chateauguay (ramp 4) and is progressing well. |
|
|
 |
The first deck section is being removed slowly. |
|
|
|
 |
It is going down to be recycled. |
|
|
|
 |
Iron Workers prepare the steel structure for the reception of the new deck. |
|
|
|
 |
New deck panels are lifted above the structure. |
|
|
|
 |
The first deck panel is ready to be installed. |
|
|
|
 |
The first deck is in place, it will be soon ready to receive the expansion joint. |
|
|
|
 |
Installation of the 14th deck panel; there remains 135 more for this ramp. |
|
|
|
JUNE 2009
|
|
|
Steel works are going on under ramp 4 and 3.
Moreover the Contractor is getting ready to start the deck replacement works of ramp #4. |
|
|
|
Installation of the signalization for detour roads. |
|
|
|
|
Closure of Ramp 4 (from Châteauguay to Montreal). |
|
|
|
|
Removal of light poles on Ramp 4. |
|
|
|
|
Marking before cutting the deck. |
|
|
|
|
Cutting the old concrete deck. |
|
|
|
|
Arrival of the 700t crane. |
|
|
|
MAY 2009
|
|
|
|
Steel works are going on under ramp 4 and 3.
Ramp 4 (from Chateauguay to Montreal) crosses over Ramp 2 (between Montreal and La Prairie). |
|
|
|
 |
This ramp’s configuration requires special work platform installation. |
|
|
|
 |
These works require some lane closures on ramp 2. |
|
|
|
 |
A clearance marker has been erected to control the truck height. |
|
|
|
APRIL 2009 |
|
|
Detour roads have to be constructed for the deck replacement on the ramps.
The steps for the construction of a road are the followings: |
|
|
 |
Foundation. |
|
|
|
 |
Road pavement. |
|
|
|
 |
Pavement compaction. |
|
|
|
 |
Installation of temporary light poles. |
|
|
|
MARCH 2009 |
|
|
 |
Platforms installation under ramps 3 and 4 are almost finished. |
|
|
|
 |
Production of prefabricated panels for the deck replacement continues. |
|
|
|
|
Reinforced or repaired elements during March are the following: |
|
|
|
 |
Main girder. |
|
|
|
 |
Floorbeams. |
|
|
|
 |
The contractor has begun the construction of the detour road. |
|
|
|
FEBRUARY
2009 |
|
|
|
Platforms have been installed under the steel structure of Ramp 4. |
|
|
 |
Under the ramps, platforms are installed with boom trucks. |
|
|
 |
Platforms are installed over the entire length of Ramp 4. |
|
|
 |
Platforms, larger than the bridge, offer a roomy and safe work zone. |
|
|
|
Repairs and reinforcing steel works have started on the steel structure of Ramp 4.
These works will be carried out in the following stages: |
|
|
 |
Rivets removal. |
|
|
 |
Replacing rivets by bolts. |
|
|
 |
Preparing surfaces, by removal of paint and rust. |
|
|
 |
Installation of the new plates. |
|
|
|
JANUARY
2009 |
|
|
|
Prefabricated panels, elements of the new deck, are made in a factory. They are stored at the factory before being transported to the work site. |
|
|
Foreseen works schematics. |
|
|
|
MAY TO DECEMBER 2008 |
|
|
|
Platforms were being
installed in Sector B1 and on about half of Sector B2.
Steel works in sector B1. |
| |
|
 |
In Sector B1, platforms are being installed with skylifts. |
| |
|
 |
For Sector B2, platforms were assembled on the shore. |
| |
|
 |
Platforms were then transported by boat and lifted under the structure. |
| |
|
|
In Sector B2, scaffoldings were erected on each side of the structure to perform work on the trusses. |
| |
|
|
Reinforcing gusset plates, by adding new steel plates, is the major work in this area. Lattice bars join in nodes where gusset plates connect them. |
| |
|
|
The first operation on the nodes is to remove the rivets and to replace them by bolts. |
| |
|
|
Reinforcing plates are fabricated in the shop. |
| |
|
|
New reinforcing plates are ready to be installed. |
| |
|
|
New plates are added one by one in a predefined order.
|
|
|
|
|