|
The
Jacques Cartier Bridge
Construction
For quicker surfing, click on the desired
topic from the drop-down list.
Construction
Cost
The
initial cost of building the bridge was approximately $20,000,000,
including expropriation expenses. If
the approaches are included, the cost was $23,000,000.

1st
Awarded Contract - South Shore Piers (May 22, 1925)
The
first contract, in the amount of $936,000, was awarded on May 22, 1925 to
Quinlan, Robertson and Janin Limited for the piers on the south part of
the bridge.

2nd
Awarded Contract - Piers and North Approaches
(Summer 1925)
In
the late summer of 1925, Dufresne Construction Co. Limited obtained a
$125,000 contract for the piers and approaches on the north part of the
bridge.

Superstructure
Erection Contract (October 25, 1925)
The
contract to erect the steel superstructure, worth $6,954,000, was awarded
to the lowest bidder, Dominion Bridge Company Limited, on October 25,
1925.

Pier
24 Construction - a Major Challenge
The
caissons used to construct the piers were built by Canadian Vickers. They
were then towed by tugs from the firm's workshops to the exact location of
each pier. Construction of pier 24, one of the two main piers supporting
the structure's cantilever section, presented the most problems and was in
itself a considerable challenge for the engineers. The pier was anchored
in the river bed and the friable soil made it necessary to dig 11 feet
(3.35 m) deep to make it solid. To fill the pier, 3,775 cubic yards (2,886
m) of concrete were required, while above water, 23,000 cubic yards
(17,584 m) of concrete and 100 tons of steel were needed. The caisson
used to build it was 128 feet (39 m) wide, 52 feet (15.8 m) deep and
weighed 1,030 tons. It
cost $500,000, an astronomical amount at the time!

Construction of the
Superstructure (Septembre 1926 to Septembre 1929)
Construction
of the superstructure took place between September 1926 and June 1928 on
the South Shore, from October 1928 to February 1929 on the Montreal shore,
and from May 1927 to September 1929 in the centre. Construction of the
main span in the central, cantilevered section presented a number of
difficulties. This type of structure has three distinct sections, namely
two anchor arms between the shores and the piers, and two cantilever arms
located on either side of the suspended span in the centre. The
cantilevered sections have to be built out from the piers towards one
another, piece by piece, panel by panel. Each side has to remain in
constant balance as it is extended out into space. The sections must be
erected and aligned with exact precision so that both halves of the
suspended span meet and can be joined together.

Last Girder
(July 10, 1929)
The
last girder joining the two sections of the bridge was put in place on
July 10, 1929. The whole operation was carried out quickly and the workers
completed the operation in less than five hours without any problems. On
this occasion, the superintendents of both work sites came face to face
and shook hands. They
had just accomplished their mission brilliantly!

Quick
Completion
The
work was completed so quickly that the contractors were able to deliver
the bridge almost a year and a half ahead of schedule, in December 1929
instead of May 1931. It took four years to build, a relatively short
period at the time for an undertaking of that size. The construction also
took place without ever interfering with traffic in the St. Lawrence.

Jacking of the Bridge (1957 and 1958)
In
1957 and 1958, the deck between piers 9 and 10 had to be jacked up from
its original 40 to 120 feet (12.2 m to 36.5 m) above the water for ships
to pass through the St. Lawrence Seaway, which was under construction at
the time. This work took 16 months and cost $6,698,750. The contract was
awarded to the Dominion Bridge Company Limited, under the supervision of
consulting engineer Dr. P.L. Pratley. Thirty jacks with a capacity of
362.87 to 544.3 tons were used to raise this section of the bridge. The
work was carried out without disrupting traffic on the bridge thanks to
the installation of two temporary "Bailey" bridges.

Construction of
the Second Acess Ramp (1961)
In 1961, a second access ramp to St. Helen's Island was built downstream of the bridge in
section five to allow motorists from Longueuil to access St. Helen's Island without
having to cut across oncoming traffic from Montreal, thereby eliminating a potential
source of accidents, particularly during rush hour.
|
     
|