|
The
Honoré Mercier Bridge
Construction
For quicker surfing, click on the desired
topic from the drop-down list.
Construction
of the Piers
A
thick layer of glacier marl over the rock, the depth of the river and the
speed of the current obliged the engineers to bypass standard techniques
and devise a method to erect the bridge piers that was better suited to
these conditions.
Because of the depth of the St. Lawrence, the engineers refused to use
cofferdams, and instead chose pneumatic caissons, a construction method
that had not been used in Montreal in 25 years.
The steel walls of the caissons were built in separate parts by Dominion
Bridge at its Lachine works. They were then transported by barges from
Ville LaSalle to Dufresne Engineering's yard located downstream of the
bridge, for assembly.
Rings were welded to the outside walls to insert heavy steel piles 10
inches (0.254 m) in diameter. After they were assembled, the caissons were
attached to two beds mounted on barges solidly attached to one another and
then transported to the exact spot where the piers were to be built. The
workers drove the piles into the rings to ensure the stability of the
caissons while they were being sunk.
A batching plant that would supply the concrete for the caissons was also
installed on a barge. Another was used for the compressed air plant. The
working chambers were connected with the outside through three shafts with
airlocks. The workers used the middle shaft, while excavated materials
were removed through those on either end. The excavation work was fairly
problem-free. Blasting was even done to dislodge large chunks of rock.
However, there were problems installing the two caissons. One of them was
to be erected less than 12 inches (0.305 m) from the corresponding pier of
the old bridge, which forced the engineers to give it a special shape. Its
dimensions (32 feet by 71 feet 11 inches (9.75 m by 21.94 m)) made it too
heavy for Dufresne Engineering's shoring, so they had to have Dominion
Bridge assemble it in the Lachine Canal and float it to the bridge site.
Because of its considerable size, special shape and the strong current, a
barge had to be added at the upstream end of the caisson. The barge was
attached to the caisson with cables and a baffler was added to reduce its
resistance to the swift currents. At the upstream Canadian Pacific Bridge,
in a 12-foot (3.66-m) per second current, anchors were dropped from the
barge on the upstream side. Powerful winches on the immobilized barge held
the caisson for the last 599 feet, 6 inches (182.80 m) of the trip. Once
it arrived at its destination, a third cable was affixed to an attachment
point on the South Shore to bring the caisson into final position.
An adventure awaited the other caisson, which went adrift. The vibrations
caused by the strong currents broke the temporary anchoring cables and the
concrete-filled caisson grounded on a bank 999 feet, 3 inches (304.67
m) downstream from the bridge. Fortunately,
the caisson was recovered, despite the strong current.

Raising
of the Bridge Sections Straddling the Seaway
In
1958-1959, the St. Lawrence Seaway Authority raised the sections of the
bridge straddling the Seaway, which was under construction at the time.
The spans on the south side, beginning at pier 14, were jacked up to
provide clear passage for ships plying the Seaway. As a result, the raised
part of the bridge, representing half of the bridge's length, is under
federal jurisdiction.

Construction
of a Second Bridge
In
August 1963, it was felt that the Mercier Bridge's two lanes were
inadequate for the constantly increasing traffic travelling across it, so
the Quebec Department of Public Works had a second bridge built downstream
of the first. At the same time, the deck of the old bridge was modified to
match its capacity to that of its "twin." Minor changes were
also made to the piers the entire surface of each pier was covered
with a new layer of reinforced concrete and their shape was changed to
match the piers of the new bridge. The "new" bridge spans the
St. Lawrence River and Seaway along the west side of the original.
All that remains of the 1932 bridge is the section between both shores,
that is, the concrete infrastructure and steel superstructure.
By twinning the old and new bridges, the number of lanes between the two
shores was increased from two to four. Southbound traffic travels over the
old bridge while northbound traffic crosses the new one.
|
   
|